AEMO Integrated System Plan · released 25 June 2026 · the diff, the loops, the power map

The number went down.
The cost went up.

The headline optimal-development-path cost fell from $122B to $106B — a 13% cut that reads like progress. Underneath, transmission costs per kilometre rose 25–55% in real terms, 45 GW of grid-scale batteries deferred a major interconnector, and household grid demand began a structural decline. This compares the 2024 and 2026 plans, the feedback they trigger, and who gains and loses.

Headline ODP
$122B$106B
an accounting win: lower WACC, work already built, cheaper solar & batteries.
Real build cost / km
+25–55%
supply chain, labour, social licence. Harder to build than in 2024.
Household grid demand 2050
−44%
to just 20 TWh — even as EVs & appliances multiply. The revenue base erodes.
⚑ flags mark findings that surprise most readers · click any diff row to read why
⚑ FOLLOW THE MONEY

The $106B isn't the point. Where it lands is.

The headline splits across four asset classes — but they are recovered in two completely different ways. Generation and storage are mostly merchant: built by investors, recovered through the market or contracts-for-difference. Transmission is almost entirely regulated: it enters the asset base and is billed back to consumers over 30–50 years. Transmission is the smallest slice and the one that overran — and it is the slice you can't escape.

ODP CAPITAL ASSET CLASS HOW IT'S RECOVERED ↓ ODP $106B Generation / VRE $56B Storage $26B Transmission $16B Firming / gas $8B Merchant / market $77B · investors, CIS, CfD Regulated — your bill $29B · RAB, recovered 30–50 yr
15%
of the ODP is transmission — the smallest of the four blocks.
~100%
of it lands on regulated consumer bills, billed for 30–50 years.
+25–55%
unit-cost overrun on exactly that inescapable block.
Asset-class split and merchant/regulated shares are indicative, reconstructed from the 2026 ISP capital breakdown and AER recovery treatment; the $106B total and transmission overrun are from the plan and AER determinations. Flow widths proportional. NEM only; SWIS excluded (not part of the NEM).
01

The diff: ISP 2024 → ISP 2026

9 material changes
Parameter
ISP 2024
ISP 2026
Δ
Headline ODP cost (Step Change, PV)
$122B
$106B
−13%
⚑ SURPRISE

The cut is largely an artefact. Transmission WACC was re-cut from 7% to ~3% (a regulated asset earns a lower risk premium), projects delivered since 2024 drop out of the forward cost, and solar & batteries got cheaper. In delivery terms the plan is more expensive and harder to build than it was two years ago — the opposite of what the press number implies.

2024$122B
2026$106B
Transmission unit cost — overhead (real)
index 100
125–155
+25–55%
⚑ SURPRISE · the real story

Overhead lines are up 25–55% real; substations 10–35%. Drivers: materials & labour shortages, every NEM project bidding for the same crews at once, and social licence — re-routes and mitigation after inadequate prior consultation. AEMO now re-tests previously "actionable" projects against this database; some fall below the benefit threshold and get deferred.

2024100
2026~140
Grid-scale BESS pipeline
17 GW
45 GW
+165%

The single biggest structural shift in the plan. Batteries become the largest source of dispatchable capacity through the 2030s, ahead of coordinated household CER and supplemented by Snowy 2.0 and Borumba. This is the force that defers transmission (see row 8) and rewires the whole least-cost calculus.

202417 GW
202645 GW
Household grid-supplied demand, 2050
~36 TWh
20 TWh
−44%
⚑ SURPRISE

No precedent in 25 years of the NEM. 36% of suitable homes already have rooftop solar; ~600,000 have batteries; on 4 Oct 2025 CER met >60% of demand for the day. Customers keep connecting (+5.8%) while energy through the network falls — transmission-to-distribution volume is already down ~10% (≈14 TWh) since FY19. The revenue base is decoupling from the asset base.

2024 traj.36 TWh
2026 traj.20 TWh
Coal retirement (NEM-wide)
earlier
by 2049
later

Queensland's LNP Energy Roadmap keeps coal running, pushing the NEM-wide exit out to ~2049. QLD consumers now pay twice: for ageing, less-reliable coal and for the infrastructure meant to replace it. A delayed exit also raises system risk if replacement capacity arrives late.

2024 plan~2038–43
2026 plan2049
New transmission length (ODP)
~7,500 km
~6,000 km
−1,435

~1,435 km less new transmission than 2024 projected. Less wire is needed because batteries firm within regions instead of moving power between them. Fewer kilometres, but each one costs much more — the net is a flatter, battery-heavier topology.

2024~7,500
2026~6,000
Transmission net market benefit
~$22B
$30B
+36%

Actionable + future projects save consumers ~$30B versus a no-transmission counterfactual — rising to $61B under a Higher-Demand (data-centre) sensitivity. On about $6B of transmission investment — roughly 6% of the $106B ODP — that is the headline case for building. The benefit grows precisely because the coal-exit and data-centre scenarios are higher-stakes.

2024$22B
2026 · high-dmd$30 / 61B
QNI Connect (QLD–NSW interconnector)
Actionable
Future ISP
demoted
⚑ SURPRISE · batteries beat wires

The clearest causal signal in the plan: a $5B+ interconnector, previously actionable, was demoted to Future ISP because 45 GW of grid-scale BESS now commoditises inter-regional firming more cheaply. If this repeats, TNSPs face stranded-asset risk on 30-year regulated investments. Storage didn't just enter the merit order — it started rewriting the transmission map.

2024  ▸ ACTIONABLE — RIT-T to proceed
2026  ▸ FUTURE ISP — needs further dev
cause: BESS substitution + higher tx cost
Home batteries installed
~150k
~600k
+300%

~600,000 households now have batteries — more than half installed in the last year alone under the federal rebate. This is the accelerant behind the demand collapse (row 4) and the death-spiral loop. Yet AEMO actually revised down coordinated-CER (VPP) assumptions — the AER queried the inconsistency — because consumer batteries can't be cycled like merchant BESS.

2024~150k
2026~600k
02

The system, on three dials

drag · the loops respond live

A stylised model of the plan's own logic. Move household CER, the battery pipeline, and the real cost of wires, and watch the outputs and feedback loops respond. Directions are faithful to the ISP; magnitudes are illustrative, not forecasts.

Household CER intensity {{ cer }}
grid-reliantself-sufficient
Grid-scale BESS pipeline {{ bess }} GW
17 (2024)80
Transmission real cost index {{ txPct }}
−20%+80%
ODP build cost (real)
${{ odp }}B
Tx net market benefit
${{ netBenefit }}B
Household grid demand 2050
{{ household }} TWh
Non-CER bill burden 2040
+${{ nonCer }}/yr
Actionable tx projects
{{ projects }}
QNI Connect interconnector
{{ qniText }}
Active feedback loops · spin rate = intensity
R
R1 · CER price death-spiral {{ r1Pct }}
↑CER → ↓throughput → ↑$/kWh → ↑self-consumption value → ↑CER. Reinforcing, already running.
B
B1 · Battery substitution {{ b1Pct }}
↑BESS → ↑intra-region firming → ↓need for new interconnectors → defer QNI-type wires. Balancing, newly dominant.
R
R2 · Tx cost–benefit trap {{ r2Pct }}
↑cost → ↓projects approved → ↑stranding risk in coal-exit zones → ↑value of the very wires now too dear to build.
⚑ THE DAMNING INSIGHT
Behind these sits B2 — regulatory lag: ~15 years from a problem being identified to a phased rule fix. The loops above act within one to two years; the rules arrive about a decade later.
03

The four-way conflict

click an actor

The plan's deepest tension isn't technical — it's that four actors' incentive gradients point in contradictory directions. Each is behaving rationally inside its own revenue model. The conflict is structural, not behavioural.

fixed-cost split substitution risk dispatch vs power quality
RAB +
revenue
cap
{{ actorName }}
Primary goal
{{ actorGoal }}
Revenue model
{{ actorRev }}
Structural incentive
{{ actorInc }}
The conflict
{{ actorConflict }}
04

Winners & losers, 2026 → 2028

↑ Structural winners
Grid-scale battery developers

45 GW queued; now the central dispatchable technology. They deferred an interconnector.

Households with CER already installed

Outsized bill cuts vs their network-cost contribution — protected by a 10-year reform glide-path starting ~2030.

Data-centre developers

Even +39 TWh of load doesn't break the ODP — a bankability signal. Can even firm the grid by chasing solar.

AEMO (institutional scope)

First Demand Side Factors statement; new mandate over data-centre & large-inverter standards.

↓ Structural losers
Non-CER consumers — renters, low-income, apartments

Carry a rising share of fixed network cost: up to +$250/yr by 2040 absent reform. An upward, regressive cross-subsidy.

TNSPs exposed to battery substitution

30-year regulated assets deferred as storage commoditises firming. Early works & social-licence spend at risk.

DNSPs under the current RAB model

Throughput decline erodes returns; the volumetric revenue model must be redesigned before ~2030.

Queensland consumers

Pay for ageing coal to 2049 and its eventual replacement.

The one line to take away

The 2026 ISP is sound planning meeting a delivery machine that can't keep up — and a revenue model wired for a one-way grid in a two-way world. The cost fell on paper while the system grew more expensive, more battery-shaped, and more politically combustible underneath.

05

ISP 2024 → 2026: what can we learn

root cause & canonical lessons

The most useful thing in the 2026 ISP is not its forecast — it is the size of the correction from 2024. In eighteen months, AEMO's own roadmap moved further than the decades-long transition it claims to chart. The size of that correction is the lesson: it points to one root cause and several conclusions that hold beyond this plan.

Coal exit (NEM)
2038 → 2049
+11 years, revised in 18 months.
Transmission cost
$16B → ~$40B
"13%, cheap insurance" → ×2.5 historical blowout.
VPP coordination
53% → <5%
Assumed orchestration vs real enrolment.
Household bills
−10% → rising
Promised fall → rising network charges.
Δ measured ISP 2024 (Jun 2024) → ISP 2026 (Jun 2026). Cost & VPP figures: AER project determinations + 2025 IASR submissions; blowout factor is an independent prior, not an AEMO estimate.
⚑ THE PRIOR, UPDATED

Treat ISP 2024 as a prior. Let two years of data update it.

Each 2024 central estimate is a prior distribution. The 2026 actuals are the likelihood. Drag the dial: at full trust in AEMO's plan the posterior stays near the 2024 number; as you let the evidence speak, it snaps toward what actually happened — and the four parameters update in the same direction, away from the optimistic edge.

Trust in AEMO's 2024 prior {{ trust }}% · {{ trustLabel }}
trust the 2026 datatrust the 2024 plan
{{ b.label }} {{ b.postLabel }}
prior {{ b.priorLabel }} 2026 actual {{ b.dataLabel }}
Grey = ISP 2024 prior · gold = posterior · red line = 2026 observed. A conjugate-normal update; prior widths and the trust dial are illustrative, the prior/observed values are from the diff ledger above. The posterior narrows as it learns — certainty rises precisely as the central case is proven optimistic.
5.1
Root cause

Optimistic inputs compound through the optimiser

⚑ CANONICAL LESSON

The ISP is a least-cost optimiser fed point estimates — and almost every uncertain input was set at its optimistic edge: GenCost cost-decline curves, 53% of home batteries orchestrated into VPPs, social licence treated as a schedule risk rather than a costed line item, ageing-coal reliability held flat, and a 2,000-strong atlas of pumped-hydro sites treated as buildable when Queensland's own process advanced two. Each assumption is individually defensible. Run them through a cost-minimiser and the optimism doesn't average out — it multiplies, producing an "Optimal Development Path" that was never a feasible development path. The headline $122B→$106B fall is the same effect in miniature: a lower discount rate makes a system that became harder and more expensive to build look cheaper.

5.2
Systems thinking

The ISP optimises a snapshot; the NEM is a feedback system

The ISP optimises a snapshot of 2050 and assumes the world holds still on the way there. But the NEM is a closed-loop control problem — long delays, strong feedback, and behaviour that reacts to the plan itself. Least-cost optimisation is open-loop: it feeds a target forward and assumes delivery. Four things systems thinking sees that the optimiser cannot —

Feedback is endogenous

The CER death-spiral, social-licence cost loops, RAB arbitrage and demand destruction are caused by the plan's own prices — not external shocks the model can bracket as "sensitivities."

Behaviour is a game, not a dial

Household battery coordination isn't a dial you set to 53%. Because most people keep their battery for their own backup, real participation settles near 1 in 5 — they won't hand an operator control just because the model needs them to.

Delays dominate

6–12 years from "actionable" to consumer impact, against a rulebook that takes ~15 years to change. Decisions land long after the conditions that justified them have moved.

Robustness > optimality

A controller senses error and corrects each cycle. A roadmap commits capital to one forecast and discovers the error only after it is sunk.

5.3
Ideology · the swerves

Where ideology overrode the least-cost outcome

⚑ CAUSATION, NOT CORRELATION

Four 2024 commitments that 2026 walked back. In each, a policy or financing preference was overruled by thermodynamics, economics or consumer behaviour — after capital and corridors had already been committed.

Hydrogen superpower. Prior: export sunshine as hydrogen. Reality: a ~56% conversion chain — green iron captures far more value per kWh. Outcome: deprecated to a sensitivity; the grid is no longer planned around it.
Coal as politics. Prior: Queensland repeals its targets (Oct 2025) and keeps coal. Reality: the NEM-wide exit slips from 2038 to 2049. Cost: Queenslanders pay twice — for ageing plant and its replacement.
The orchestrated consumer. Prior: 53% of batteries dispatched as one fleet. Reality: <5% enrol; people keep control. Cost: firming must be bought as utility batteries and gas, not borrowed from households.
Wires as the safe asset. Prior: a low regulated WACC made transmission the model's cheapest firming. Reality: 45 GW of merchant batteries undercut it and demoted QNI Connect. The regulated financing advantage favoured wires; the cheapest physical firming was batteries.
5.4
2026 → 2028

Treat AEMO's central numbers as best-case, and adjust toward what's deliverable

The simplest rule the 2024→2026 record gives us for reading the next plan: don't treat AEMO's central forecast as the middle of the range. Treat it as the optimistic end, and adjust each key number toward what can realistically be built and delivered.

Input in the plan
What AEMO assumed
A more realistic read — and why
Transmission build cost
About $16B, described as cheap insurance.
Closer to $40B — roughly 2.5× higher. Big grid projects have a long history of cost blowouts once construction starts.
Coordinated home batteries
(virtual power plants)
About 53% of household batteries act together as one fleet the grid can call on.
More like 1 in 5 homes (~19%). Most people keep their battery for their own backup and won't hand an operator control of it.
Ageing coal reliability
Held roughly steady right up to retirement.
Add a breakdown penalty. Old plants fail more often as they near closure, so expect more unplanned outages.
New pumped-hydro storage
Around 2,000 candidate sites listed in the national atlas.
Only a handful actually get built. Cost, approvals and community opposition stop most — Queensland's process has advanced just two.

What 2028 will ratify — not reverse: batteries beat wires for intra-regional firming; the binding constraint migrates from transmission to the distribution edge; household grid demand keeps decoupling from connections; and the volumetric RAB / tariff model is formally reopened. The direction of every 2024→2026 swerve was toward the consumer-led, storage-heavy, distribution-constrained system — expect 2028 to make that official.

The canonical lesson of 2024 → 2026

Plan for feasibility, not optimality, and re-plan on a short cycle. The central forecast will be wrong — the 2024 plan proved that in 18 months — so what matters is how quickly the next plan corrects. A two-yearly roadmap that assumes on-time, on-budget delivery is too slow a feedback loop for a system changing this fast.

Source — AEMO 2026 Integrated System Plan & media release (25 Jun 2026); AER Transparency Review (7 Jan 2026); AEMC Pricing Review Final Report (18 Jun 2026); submissions from EUAA, APA, Transgrid, Nexa Advisory, CPA Agency, Policy Institute Australia, VFF, Solar Citizens. Probability tags are the source analysis's directional confidence estimates, not AEMO outputs. Base data reconciled with the ISP 2026 System Dynamics report.

Author: Walter Adamson | Connect www.linkedin.com/in/adamson | walter@outcomesnow.com · June 2026

Walter is Human and can make mistakes. No advice given, all care no responsibility.